SAMPLE WORKS

MLR Project Management & Consultancy prides itself in offering services of the highest quality and standards.  Below provides some of the completed works demonstrating these attributes.

Animation for Construction Planning

Project Scope: Structural modification of existing underground parking, construction of car entrance ramp, construction of floor ramp

Sector: Buildings, Infrastructure

Task Objective: Present and support the construction schedule that can be best understood by stakeholders

Results Achieved:

  • Clients were able to comprehend the construction methodology as represented in Gantt charts
  • Provided tools for planning and scheduling of the project
  • Quantity take-off for temporary works/materials were readily available
  • Provision for pedestrian access clearly identified

Animation for Construction Planning

Project Scope: Construction of car and pedestrian link bridge

Sector: Buildings, Civil, Roads, Infrastructure

Task Objective: Present and support the construction schedule that can be best understood by stakeholders, provide representation of the traffic management plan

Results Achieved:

  • Clients were able to comprehend the construction methodology as represented in Gantt charts
  • Provided tools for planning and scheduling of the project
  • Quantity take-off for temporary works/materials were readily available
  • Construction plant and equipment duly planned
  • Traffic management in the busy area clearly represented

3D Interpretation of Construction Plans

Project Scope: Construction of bridges and tunnels, road works, utility works

Sector: Civil, Roads, Infrastructure

Task Objective: Collate construction plans to render a 3-dimensional version so as to ease complexity in formulating construction approach and project estimation

Results Achieved:

  • Provided visualization of the extent of the work scope for better planning, scheduling and estimation
  • Traffic management plan was effectively planned
  • Extent of temporary works identified by superimposing the proposed modifications to the existing structures

Best Practice in Project Planning

PowerPoint presentation is available by clicking the image

Project Scope: As per contract

Sector: All Construction Projects

Task Objective: Provide an overview on the Contractor’s requirements to set-up and manage construction schedule for review and approval by the Clients

Results Achieved:

  • Construction schedules were resource and cost loaded
  • Scope of works in the schedule were aligned with the bill of quantities
  • Provided complete requirements to the Clients for review and approval of baseline construction schedule
  • Updating of the schedules were done by physical measure of the progress
  • By earned-value management, progress percentage in the schedules were aligned with the percentage reflected for interim payment applications
  • Weekly and monthly reports were submitted on time throughout the project duration

Best Practice in Project Planning

PowerPoint presentation is available on desktop view

Project Scope: As per contract

Sector: All Construction Projects

Task Objective: Provide an overview on the Contractor’s requirements to set-up and manage construction schedule for review and approval by the Clients

Results Achieved:

  • Construction schedules were resource and cost loaded
  • Scope of works in the schedule were aligned with the bill of quantities
  • Provided complete requirements to the Clients for review and approval of baseline construction schedule
  • Updating of the schedules were done by physical measure of the progress
  • By earned-value management, progress percentage in the schedules were aligned with the percentage reflected for interim payment applications
  • Weekly and monthly reports were submitted on time throughout the project duration

Project Progress Tracker

PowerPoint presentation is available by clicking the image

Project Scope: Land development and construction of 1,500 houses including associated roads and infrastructure works

Sector: Buildings, Civil, Roads, Infrastructure

Task Objective: Develop a repository of progress data for management, control and reporting of project

Results Achieved:

  • An interactive and dynamic VBA-programmed spreadsheet was developed
  • Progress actuals were recorded on a daily basis and by physical measure for analysis and reporting
  • All schedule construction activities were measured by Key Performance Indicators (KPI) against the approved baseline
  • Percent completion reflected in the Primavera P6 schedules were supported by physical measurements
  • Weekly and monthly reports were submitted on time throughout the project duration

Project Progress Tracker

PowerPoint presentation is available on desktop view

Project Scope: Land development and construction of 1,500 houses including associated roads and infrastructure works

Sector: Buildings, Civil, Roads, Infrastructure

Task Objective: Develop a repository of progress data for management, control and reporting of project

Results Achieved:

  • An interactive and dynamic VBA-programmed spreadsheet was developed
  • Progress actuals were recorded on a daily basis and by physical measure for analysis and reporting
  • All schedule construction activities were measured by Key Performance Indicators (KPI) against the approved baseline
  • Percent completion reflected in the Primavera P6 schedules were supported by physical measurements
  • Weekly and monthly reports were submitted on time throughout the project duration

Tender Project Review

PowerPoint presentation is available by clicking the image

Project Scope: Land development and construction of 1,500 houses including associated roads and infrastructure works

Sector: Civil, Roads, Infrastructure, Marine

Task Objective: Provide comprehensive review of project for tender, develop construction programme, present to management

Results Achieved:

  • Tender documents reviewed and collated pertinent information for presentation
  • Tender programme developed with the estimated resources required to complete the works as per required period
  •  Construction sequence planned accordingly to aide in the estimation of cost and time to complete
  • Presented to management the comprehensive construction planning solution

Tender Project Review

PowerPoint presentation is available on desktop view

Project Scope: Land development and construction of 1,500 houses including associated roads and infrastructure works

Sector: Civil, Roads, Infrastructure, Marine

Task Objective: Provide comprehensive review of project for tender, develop construction programme, present to management

Results Achieved:

  • Tender documents reviewed and collated pertinent information for presentation
  • Tender programme developed with the estimated resources required to complete the works as per required period
  •  Construction sequence planned accordingly to aide in the estimation of cost and time to complete
  • Presented to management the comprehensive construction planning solution