Schedule Risk Analysis With Acumen: Effects of Floats And Lags on Results

Share
Tweet
Share
Schedule Risk Analysis by MLR

This article provides an overview on how varying inputs and parameters affect the date outputs, in particular, the P0, P50, and P100 dates, in the Schedule Risk Analysis (SRA) with software Deltek Acumen Fuse.  By understanding how Acumen behaves with respect to varying conditions, schedulers, risk managers, and key stakeholders alike will be guided on providing only realistic input values for the SRA.

In this analysis, the effects of the schedule total floats and lags on SRA results or the P-values (P0, P50, P100) are investigated.  Four simple schedules were developed using Primavera P6 to understand how results varied when the same single risk was applied to a critical activity, non-critical activity, and to an activity whose criticality was driven by a lag.

The analysis proves that Acumen considers the total float in the output.  Meaning, the total float is “consumed” first before driving the linked successors to their probabilistic dates.

Variable

  • Risk Mapping, Primavera P6 Schedule Critical Activities (Case 06).

Input

  • A single risk is assigned to a critical activity (criticality driven by logic).
  • A single risk is assigned to a non-critical activity with different total float.
  • A single risk is assigned to a critical activity (criticality driven by lag).
  • 1,000 iterations set in Deltek Acumen Fuse.
  • All other parameters are set to be the same in each case/project shown in Figure 1 below.
Primavera Schedule for Risk Analysis
Figure 1. Primavera Schedule with Different Criticalities and Activity Risk Mapping.

Table 1.  Risk Mapping to Activities with Varying Criticalities.

Schedule Risk Analysis Risk Register

Output

Risk Exposure Histogram by Deltek Acumen Fuse
Figure 2. Risk Exposure Histogram Generated from Acumen (see tabulated values in Table 2).
Risk Drivers by Deltek Acumen Fuse
Figure 3. Risk Drivers Generated from Acumen (see tabulated values in Table 2).

Analysis

Tabulation of the results of Figures 2 and 3 are shown in Table 2 along with calculations for analysis.

Table 2.  Results and Calculations.

Schedule Risk Analysis

Due to the risk assigned to a critical activity, the P100 date adds 100 work days to the deterministic date (DT) in C06A. This 100 days is also the max duration set on the risk register for C06BC06C, and C06D.

The total float in C06B to which the risk was assigned is 150 days. With the max duration input of 100 days, the completion date did not move from its DT value. It seems the risk duration consumed the total float first.

To further prove C06BC06C has less total float than the risk max duration (50 days vs. 100 days). This resulted to the P100 date shifting 50 working days from the DT. The risk duration does consume the total float first before the probabilistic completion date drifts away from the DT.

In C06D, the risk is assigned to a critical activity. But unlike C06A wherein the criticality is driven by logic, in C06D the criticality is driven by the assigned lag. The results of the schedule analysis for both cases are the same.

Takeaways

  1. When the risk is assigned to a critical activity, regardless whether the criticality is caused by logic or by lag, the P100 date drifts from the deterministic date by the same max duration in the assigned risk.
  2. Acumen considers the total float. It is “consumed” first before driving the succeeding activity to its probabilistic completion date.
Share
Tweet
Share
Interactive project planning and controls dashboard using Power BI and Primavera P6 for construction schedule tracking, earned value analysis, Gantt charts, and project performance monitoring.

The Ultimate Project Planning and Controls Dashboard Using Power BI and Primavera P6

Explore a fully interactive Project Planning and Controls Dashboard built using Power BI and Primavera P6. This article demonstrates how modern construction project controls can integrate earned value management, schedule performance tracking, Gantt chart visualization, progress photos, historical schedule submissions, and Window Analysis-based delay analysis into one centralized digital reporting environment. Discover how dynamic dashboards improve project visibility, stakeholder communication, forensic schedule analysis, and decision-making while simplifying monthly reporting workflows for complex construction and infrastructure projects.

Read More »
Project planning and scheduling practices comparison across the USA, UAE, and Australia featuring construction project controls, Primavera P6 scheduling, global infrastructure, and international project management concepts.

How Planning and Scheduling Practices Differ Across the USA, UAE, and Australia

Explore the key differences in project planning, scheduling, and project controls practices across the USA, UAE, and Australia based on real industry experience. This article shares firsthand insights into USACE and NAVFAC scheduling requirements, the fast-paced construction environment of the Middle East, and the contrasting project controls culture in Australia. Learn how schedule management, delay analysis, reporting standards, cost loading, and contractual expectations vary across regions, and discover practical lessons for planners and schedulers looking to work internationally in construction and infrastructure projects.

Read More »
MLR Project Management & Consultancy | planning engineer vs scheduler comparison

Planning Engineer vs Scheduler: Key Differences Explained from Real Experience

What is the difference between a planning engineer and a scheduler? This article explains the key differences between a planning engineer vs scheduler based on real-world construction project experience. Learn how their roles, responsibilities, and skills differ, from schedule development and progress tracking to forecasting, delay analysis, and project planning strategy. If you’re a planner, project manager, or construction professional, this guide will help you clearly understand where scheduling ends and planning begins.

Read More »

Build Better Projects With Expert Guidance

MLR Subscription - Browsing

Where to send the file?