Deltek Acumen Fuse

Schedule Risk Analysis With Acumen: Effects of Floats And Lags on Results

In this analysis, the effects of the schedule total floats and lags on SRA results are investigated. Four simple schedules were developed using Primavera P6 to understand how results varied when the same single risk was applied to a critical activity, non-critical activity, and to an activity whose criticality was driven by a lag.

Schedule Risk Analysis With Acumen: Effects of Floats And Lags on Results Read More »

Schedule Risk Analysis With Acumen: Different Activity Status

In this analysis, different activity status (completed, in progress, not started) are investigated on how each affects the SRA output. A simple schedule was developed using Primavera P6 for a straightforward understanding of the relationship between the inputs and the SRA results generated from Acumen.

Schedule Risk Analysis With Acumen: Different Activity Status Read More »

Schedule Risk Analysis With Acumen: Different Activity Types

In this analysis, the activity types are varied while holding all other parameters constant. These activity types include Task Dependent, Level of Effort, WBS Summary, and Milestones. A simple schedule was developed using Primavera P6 for a straightforward understanding of the relationship between the inputs and the SRA results generated from Acumen.

Schedule Risk Analysis With Acumen: Different Activity Types Read More »

Schedule Risk Analysis With Acumen: Different Calendars

In this analysis, the effects of activity calendars in the SRA outputs are investigated. Activities are assigned with different calendars while holding all other parameters constant. A simple schedule was developed using Primavera P6 for a straightforward understanding of the relationship between the inputs and the SRA results generated from Acumen.

Schedule Risk Analysis With Acumen: Different Calendars Read More »

Schedule Risk Analysis with Acumen: Varying Activity Constraint Type

In this analysis, the activity constraint type is varied while holding all other parameters constant. A simple schedule was developed using Primavera P6 for a straightforward understanding of the relationship between the inputs and the SRA results generated from Acumen.

Schedule Risk Analysis with Acumen: Varying Activity Constraint Type Read More »